Report for November 2015
- Report Date
- November 2016
DRAFT
Achievements this period
- Post-deployment JIRA issues resolved
- New closure milestone approved
- User communicaions plan enacted
- November payslips published online in paralell with paper payslips
Issues
- Business requested extension of paralell run, requiring change of closure milestone from December to February.
Next Steps
- Business to complete paralell run
- Deployment sign-off (January)
- Close
Milestones
31-Jan-2016 | Deployment Sign off Review |
10-Feb-2016 | Close |
RAG Status
The project status is RED with no issues, as the closure milestone was moved by more than one month
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days