Report for December 2014
- Report Date
- December 2014
Achievements this period
- Brief, estimate and plan drafted
Issues
- delay to end of planning till scope and milestones agreed
- project scope for dealing with users without uuns and for resetting passwords yet to be agreed.
Next Steps
- project team to meet with sponsor to finalise scope
- achieve end of planning milestone
- Business analysis to finalise BRD
- secure resources in light of estimate, plan and milestones to be agreed in planning signoff
Milestones
12-Dec-2014 | End of Planning |
27-Apr-2015 | Delivery |
18-Jun-2015 | Close |
The project status is GREEN
- Approved budget
- 100.0 days
- Activity this month
- 8.0 days
- Activity this year
- 18.0 days
- Activity to date
- 18.0 days
- Estimate to complete current year
- 72.0 days
- Estimate to complete future years
- 0.0 days