Report for October 2016
- Report Date
- October 2016
Achievements this period
- No IS activity planned this month
- Business carrying out testing of paralelle run and selected online payslips in in LIVE
Issues
- Business likely to request extension of paralell run, requiring change of closure milestone from December to February.
Next Steps
- Business to complete testing of paralell run and selected online payslips in LIVE
- Business to commence user communications announcing delivery of online payslips later in the year
- Deployment sign-off (December)
- Delivery of online payslips for all users (December)
- Close
Milestones
01-Dec-2016 | Deployment Sign off Review |
09-Dec-2016 | Close |
RAG Status
The project status is AMBER as there is a risk that the closure milestone may be moved by more than one month
- Approved budget
- 274.0 days
- Activity this month
- 6.5 days
- Activity this year
- 18.0 days
- Activity to date
- 259.0 days
- Estimate to complete current year
- 9.0 days
- Estimate to complete future years
- 0.0 days