Report for September 2016
- Report Date
- September 2016
Achievements this period
- UAT completed and Acceptance sign-off achieved
- Delivery achieved
Issues
- Minor issues not picked up in user-acceptance testing
Next Steps
- Business to commence user communications announcing deliver of online payslips later in the year
- Deployment sign-off (December)
- Delivery of online payslips for all users (December)
- Close
Milestones
01-Dec-2016 | Deployment Sign off Review |
09-Dec-2016 | Close |
RAG Status
The project status is GREEN
- Approved budget
- 274.0 days
- Activity this month
- 6.5 days
- Activity this year
- 18.0 days
- Activity to date
- 259.0 days
- Estimate to complete current year
- 9.0 days
- Estimate to complete future years
- 0.0 days