Report for July 2016
- Report Date
- July 2016
Achievements this period
- new paper payslip (PAY31) signed off in TEST
Issues
- Acceptance review milestone missed due to issue with delivery of online payslip
- Acceptance, delivery and closure milestones will require to be replanned
- Production resources may be difficult to assign for UAT/delivery in July/August (Item 50)
Next Steps
- Clarify plan for delivery of online payslip with business and any associated risks
- Acceptance, delivery and closure milestones will to be replanned
- IS-authoried Online payslip to be delivered into TEST
Milestones
29-Jul-2016 | Acceptance Review |
08-Aug-2016 | Delivery |
05-Sep-2016 | Deployment Sign off Review |
26-Sep-2016 | Close |
RAG Status
The project status is AMBER due to the issues with the delivery of the online payslip by the business.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days