Report for June 2016
- Report Date
- June 2016
Achievements this period
- Enhanced scope confirmed with project sponsor ( Item 49)
- New development resource recruited and introduced to project
- New milestones agreed with project sponsor
Issues
- Business (payroll) may not be able to deliver online payslips in August
- Production resources may be difficult to assign for UAT/delivery in July/August (Item 50)
Next Steps
- Sign off new paper payslip in TEST
- Clarify delivery of online payslip with business and any associated risks
Milestones
11-Jul-2016 | Build Review |
29-Jul-2016 | Acceptance Review |
08-Aug-2016 | Delivery |
05-Sep-2016 | Deployment Sign off Review |
26-Sep-2016 | Close |
RAG Status
The project status is RED as the new milestones agreed have been moved by more than a month and as the delivery of the online payslip by the business may not now be achievable in August.
- Approved budget
- 274.0 days
- Activity this month
- 10.0 days
- Activity this year
- 70.0 days
- Activity to date
- 223.0 days
- Estimate to complete current year
- 34.0 days
- Estimate to complete future years
- 9.0 days