Report for May 2016
- Report Date
- May 2016
Achievements this period
- Password reset and UUN/Email updates delivered into LIVE
- Project replanning discussed with IS project team, sponsor and business leads
- New milestones proposed
- Development resource assigned (contractor) to deliver new paper payslip deliverable
- Outstanding PAY30 JIRA addressed:https://www.jira.is.ed.ac.uk/browse/PPP002-31
- Estimates delivered to create new paper payslip deliverable ("PAY31") and to update PAY30 with enhanced scope
- E-recruitment and PAY30 deliverables re-deployed to TEST
- UAT of E-recruitment deliverable underway
Issues
- Enhanced scope to be confirmed with project sponsor ( Item 49)
- Development resource departing early June - new development resource will have to be recruited ( Item 49)
- Newly agreed milestones will not be achievable given departure of development resource ( Item 49)
- Production resources may be difficult to assign for UAT/delivery in July/August (Item 50)
Next Steps
- Secure new developer resource
- Re-plan project and agree new milestones
Milestones
Please note these published milestones will not now be achievable
11-Jul-2016 | Build Review |
29-Jul-2016 | Acceptance Review |
08-Aug-2016 | Delivery |
05-Sep-2016 | Deployment Sign off Review |
26-Sep-2016 | Close |
RAG Status
The project status is RED as a new developer resource will have to be hired.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days