Work completed
- The Project Board met on 9th October and approved the Project Brief and major milestones
- A risk register has been circulated to the Project Board
- The Working Group is meeting two-weekly
- Discussions about which platform will be used for the migration are in progress
- Audit of stack, servers and domains provided to CHSS
- Google analytics ownership has been transferred to CHSS
- Information has been collated about uptake of SCOT toolkit and other CHSS websites in past 12 months
- Payment schedule has been agreed
Issues
What's next
- Project plan to be completed
- Recruitment of additional staff to be progressed
- Platform to be agreed (WordPress or Drupal)
- Module for test migration to be agreed; migration to be scheduled (November)
- Modules to be prioritised for migration order
- Next Working Group meeting 11th November 11am
- Next Project Board meeting 10th November (email only)
- Transfer of domains & certificates to be scheduled (January)
- Approved budget
- 110.0 days
- Activity this month
- 4.0 days
- Activity this year
- 4.0 days
- Activity to date
- 4.0 days
- Estimate to complete current year
- 106.0 days
- Estimate to complete future years
- 0.0 days