Project Status Reports

Title Report Date Time Cost Scope Overall Change
Timelines confirmed and migration ready to start December 2019 GREEN GREEN GREEN GREEN No Change
Test module migration in progress November 2019 GREEN GREEN GREEN GREEN No Change
Project Planning in progress October 2019 GREEN GREEN GREEN GREEN

Project Info

Project
CHSS eLearning Migration
Code
P0339
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Karen Beggs
Project Sponsor
Anne-Marie Scott
Current Stage
Deliver
Status
In Progress
Project Classification
Run
Start Date
01-Oct-2019
Planning Date
01-Nov-2019
Delivery Date
29-May-2020
Close Date
31-Jul-2020
Overall Priority
Normal
Category
Discretionary

Documentation

Not available.