Status report for period ending 4 October 2019

Report Date
October 2019

Key Activities/Milestones since last report

Key Activities since last report

Policy and TOM development workshops have been completed 

Draft TOM has been written and an overview provided to the participants in the working group who contributed to the drafts.  They support the model proposed. 

Upcoming Activities/Milestones

Upcoming Activities

Meeting with internal audit to review the proposed TOM against the outcomes of the 2016  Audit  of Policy Management 

Draft paper to go to the SEP board (31 Oct)  outlining the principles for policy management and the TOM 

 

 

 

 

Upcoming Milestones

None this period 

 

 

Key Risks and Issues

 
New/Changed Risks

Nothing to report this period 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
The project is on track and there are no imminent significant risks in this phase of work
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
University Policy Framework
Code
P0326
Management Office
Service Excellence PMO
Project Manager
Ruth Wilson
Project Sponsor
Tracey Slaven
Current Stage
Plan
Status
In Progress
Project Classification
Transform
Start Date
31-Oct-2018
Planning Date
11-Feb-2019
Delivery Date
08-Dec-2019
Close Date
20-Dec-2019
Overall Priority
Normal
Category
Discretionary

Documentation