Report for October 2019

Report Date
October 2019

Achievements

  • None

Issues

Next Steps

  • Await update from issue
Project Status
RAG Status
Time
RED
Cost
RED
Scope
RED
Overall
RED
RAG Commentary
BA working on initial requirements was re-assigned to CORE systems programme. Business analysis needs to be completed to inform the shape of the project (i.e. procurment, improvement or new development). Delay in requirements gathering will cause issue with strating & scoping the project. The current applications will not scale anmd needs to be replaced in this session. Newly recruited BA has been assigned to the project - start on 4 Nov.
Change Status
Has formal escalation taken place?
Yes
Escalated to
Programme Owner, POrtfolio Owner, Head of Project Services, IS Applications Director, ISG CIO
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
BMS - Honours Project Portal Future Support
Code
MVM516
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Susan Ridder-Patrick
Project Sponsor
Michael Shipston
Current Stage
Initiate
Status
In Progress
Project Classification
Grow
Start Date
01-May-2019
Planning Date
n/a
Delivery Date
01-May-2020
Close Date
n/a
Overall Priority
Normal
Category
Discretionary

Documentation