December 2018
- Report Date
- December 2018
Achievements
- Presenter PC for Vet School room G.01 purchased early due to issues reported by local support team.
Next Steps
- Identify suitable dates for ordering and delivery of PCs for all necessary sites.
- WGH MEC will require careful consideration due to planned refurbishment of the floor which will remove storage locations for new PCs.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years