April 2016

Report Date
April 2016

Achievements in Last Period

  • resource decisions - not achieved
  • decide if we need ot wait for Windows 10 to be in place - not achieved
  • complete brief if project to proceed - not achieved

Issues and Risks

  • need decision on resource for the project
  • need a decision on resource for support  
  • Next Steps
  • suspend project
  • meeting with directors
  • decide if project to proceed, and when, and scope

Milestones

 

TBC

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
AMBER
Overall
AMBER
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Integration and adoption of ISFM
Code
MVM024
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Muriel Mewissen
Project Sponsor
Paul Clark
Current Stage
Close
Status
Closed
Start Date
28-Oct-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
13-Jan-2017