Organisation
Work/Task Breakdown, Resources Skills and Cost
Project Manager - 1 day
Business Analysis
8 days estimate
1. Meet with Caroline Brett - w/c 1/6 2. Create first draft of the IGT requirements (highlight initial thoughts on whether there are standard/generic or project specific/non generic documents available) - by 5/6 3. Match standard documents to IGT requirements and create links in the spreadsheet - by 12/6 4. Meet with the group for initial review - w/c 15/6 5. Amendments to the standard documents and updates following the initial review - by 19/6 6. Produce IT documentation checklist - by 25/6
8 days estimate a. Initial draft (4 days) b. Meet with group for review (1 day) c. Update and store templates and create links (3 days)