Report for December 2015
- Report Date
- December 2015
Achievements in Last Period
- UAT performed.
- Awaiting outcome of CO investigation of synchronisation problem.
Issues
The UAT was not successful: new issues were reported. There is no budget remaining to address the issues. This is noted in https://www.projects.ed.ac.uk/project/mvm005/issues/16
As noted for the last two months:
- Synchronisation with Outlook is failing on the business's new PCs. The PM and developer have recommended that the MVM CO's investigate this problem. This is noted in https://www.projects.ed.ac.uk/project/mvm005/issues/14
- The business have requested further changes but there is no agreement in place for funding further work. This is noted in https://www.projects.ed.ac.uk/project/mvm005/issues/13.
RAG status set to RED because the way forward needs to be agreed before budgets can be resolved and new milestones set.
Next Steps
- Discuss options for further work.
- Await outcome of CO investigation of synchronisation problem.
| 04-Dec-2015 | Acceptance Sign-off | Accept |
| 18-Dec-2015 | Closure | Close |
| 18-Dec-2015 | Deployment Sign-Off | Deliver |
- Approved budget
- 34.0 days
- Activity this month
- 0.0 days
- Activity this year
- 4.0 days
- Activity to date
- 36.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days