Estimate of Work to complete after meeting - 28/1

 

Estimates from Greg - approved by Project Manager

 

  1. Revision of logic in calendar to deal in Events as primary working unit instead of Volunteers, including:
  • creation of interfaces for adding/creating/editing events
  • Revision of volunteer interface to be subordinate to Events
  • Addition of colour marking and invoice flagging to events
  • Adding logic for cancellations by volunteers

5 days

It does take a bit of thought to do right/well

  1. Revision of existing forms to have the same ‘look and feel’ throughout, addition of unlimited comment field to existing people form

0.5 – 1 day

  1. Revision of reports and letters

1.5 days

  1. Creation of new shared calendar and integration. Mainly checking Outlook’s capabilities

1 – 1.5 days

 

8 – 9 days approximately.

Project Info

Project
Simulated Patient Enhancements
Code
MVM005
Programme
MVM Business Administration (MVMBUS)
Project Manager
Maurice Franceschi
Project Sponsor
Keith Wylde
Current Stage
Close
Status
Closed
Start Date
13-Oct-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Mar-2016
Programme Priority
5
Overall Priority
Normal
Category
Discretionary