October 2015
- Report Date
- October 2015
Achievements in Last Period
The PM and developer met with the business lead to review the issues raised during further UAT. Bugs preventing correct operation of the current functionality were fixed and returned for further testing.
Issues
- Synchronisation with Outlook is failing on the business's new PCs. The PM and developer have recommended that the MVM CO's investigate this problem. This is noted in https://www.projects.ed.ac.uk/project/mvm005/issues/14
- The business lead has not been able to test the latest fixes in the agreed time and so the milestones will need to be revised. This is noted in https://www.projects.ed.ac.uk/project/mvm005/issues/13, although the date noted in that issue has also been missed.
- The business have requested further changes but there is no agreement in place for funding further work. This is noted in https://www.projects.ed.ac.uk/project/mvm005/issues/13.
- The budget has been exceeded by a couple of days.
RAG status set to RED because milestones & budget need to be agreed, along with resolution of request for further work.
Next Steps
- Await outcome of testing the latest fixes.
- Await outcome of CO investigation of synchronisation problem.
- Discuss options for further work.
| Target date | Previous date | Title |
|---|---|---|
| 02-Oct-2015 | 14-Aug-2015 | Acceptance Sign-off |
| 16-Oct-2015 | 28-Aug-2015 | Closure |
| 16-Oct-2015 | 28-Aug-2015 | Deployment Sign-Off |
- Approved budget
- 34.0 days
- Activity this month
- 2.0 days
- Activity this year
- 3.0 days
- Activity to date
- 36.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days