Report for September 2015
- Report Date
- September 2015
Achievements in Last Period
Nothing to report as the business were not able to test until the end of the month
Issues
Testing raised further issues. These will be reviewed on Oct 7th.
Next Steps
Determine what would be needed to resolve the issues.
The project status is Amber because the issues may require more time and effort. The funding for any further work is unclear.
| Target date | Title |
|---|---|
| 02-Oct-2015 | Acceptance Sign-off |
| 16-Oct-2015 | Closure |
| 16-Oct-2015 | Deployment Sign-Off |
- Approved budget
- 34.0 days
- Activity this month
- 0.2 days
- Activity this year
- 1.2 days
- Activity to date
- 33.9 days
- Estimate to complete current year
- 0.5 days
- Estimate to complete future years
- 0.0 days