Report for September 2015

Report Date
September 2015

Achievements in Last Period

Nothing to report as the business were not able to test until the end of the month

Issues

Testing raised further issues.  These will be reviewed on Oct 7th.

Next Steps 

Determine what would be needed to resolve the issues.

The project status is Amber because the issues may require more time and effort.  The funding for any further work is unclear.

 

 

Target dateTitle
02-Oct-2015Acceptance Sign-off
16-Oct-2015Closure
16-Oct-2015Deployment Sign-Off
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
34.0 days
Activity this month
0.2 days
Activity this year
1.2 days
Activity to date
33.9 days
Estimate to complete current year
0.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Simulated Patient Enhancements
Code
MVM005
Programme
MVM Business Administration (MVMBUS)
Project Manager
Maurice Franceschi
Project Sponsor
Keith Wylde
Current Stage
Close
Status
Closed
Start Date
13-Oct-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Mar-2016
Programme Priority
5
Overall Priority
Normal
Category
Discretionary