End of August 2017
- Report Date
- August 2017
Activities during the period:
- uun@ed.ac.uk was implemented by ITI on Monday the 21st of August.
- All appropriate permissions for the use of data have been received.
- Deployment Checklist signed off.
Issues arising:
- None
Key activities planned for next month:
- Go Live
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days