Project journal

Title Description Author Post date
Week ending 15th March 2013
  • Meeting with ITI Unix to resolve outstanding questions on mount sizes, naming, etc.
  • Test migration carried out; results circulated to project team
  • Work started on rman database & configuration
  • Further testing of performance on SAN carried out
  • Database standards updated after review by technical teams
David Watters 19-Mar-2013
Week ending 8th March 2013
  • Group meeting to discuss new database standards
  • Database standards agreed by group and susbsequently published
  • Rman environment prepared and rman catalog created
  • Work started on documenting the new backup standards and principles
  • Migration documents started but no migration attempted yet
  • Presentation on new infrastructure at Staff Meeting by Project Sponsor & Senior Supplier

 

David Watters 19-Mar-2013
February 2013
  • Work on build continued; more performance testing carried out
  • Clarification on deliverables for project leading to new estimates and WBS
  • Prioritisation of deliverables agreed with project team
  • Project plan & milestones updated
  • New milestones approved by WIS
  • Discussions with Service Management about migration
David Watters 08-Mar-2013
January 2013
  • Build of new servers continued by ITI Unix; some network issues encountered but eventually resolved
  • New servers released to IS Applications
  • Work on configuring new servers started by Dev Tech; first database built
  • Initial discussions on which database to move first
  • Documentation on standards started
  • Initial performance tests carried out with positive results
David Watters 08-Mar-2013
Week ending 21st December 2012
  • Work progressed on server build - estimated ready date now c. 14/01/13
  • Project plan & bookings to be revised - unable to complete due to staff leave
  • Meetings postponed because of staff leave
David Watters 21-Dec-2012
Week ending 14th December 2012
  • Servers delivered but resource not immediately available in ITI to commence build
  • Meeting of project team in IS Apps to list processes and policies to be developed
  • Discussions around which databases to migrate started (MyEd and BBL strong favourites)
  • Senior supplier is now Iain Fiddes (Dave Berry to continue in consultative role)
David Watters 21-Dec-2012
Week ending 7th December 2012
  • Dev Tech resource conflicted for HR project
  • Delivery date for servers pushed back to mid-December
  • Bookings and milestones to be reviewed again and updated
David Watters 07-Dec-2012
Week ending 30th November 2012
  • Colleagues from Dev Tech and Tech Management attended 4-day ADG training course
  • ITI Unix advised us of initial delay to delivery of servers
  • Attempt to negotiate earlier delivery of two servers for DEV environment
  • Agreement that if DEV servers delivered on time, then work can progress on these
David Watters 07-Dec-2012
Week ending 23rd November 2012
  • TAD finalised and distributed for review by stakeholders
  • TAD discussed and signed off at PPDR
  • Details on server volumes ironed out by stakeholders
  • TAD updated with details on database mounts
David Watters 07-Dec-2012
Week ending 16th November 2012
  • Work continued on Technical Architecture Document
  • TAD reviewed by Dev Tech team
  • Hardware order submitted and delivery date received (03/12)

 

David Watters 16-Nov-2012
Week ending 9th November 2012
  • Quotes received by ITI Unix for servers
  • Work started on Technical Architecture Diagram
  • Project website and ASTA updated
David Watters 08-Nov-2012
Week ending 2nd November 2012
  • Plans in ASTA updated
  • Resource requests updated for Build & Acceptance
  • Resources assigned to early tasks for project
  • Revised milestones advised to WIS
  • Revised milestones approved by WIS
David Watters 08-Nov-2012
Week ending 28th September 2012
  • Training had to be rebooked because of delay to PO
  • Discussion around virtualisation postponed (till 03/10)
  • Plan input into ASTA and initial booking requests submitted
  • First weekly meeting with Programme owner - concerns around timing and bookings expressed
David Watters 02-Oct-2012
Week ending 26th October 2012
  • ITI Unix contacted again about machine specs and delivery dates
  • Meeting between PM, Programme Manager and Resource Manager - resources sorted out for November/December
  • Project plan redrafted
  • Meeting with Senior Supplier, Sponsor and PM
David Watters 26-Oct-2012
Week ending 19th October 2012
  • Resourcing issues still not resolved
  • Issue reported to WIS
  • Senior Supplier (Dave Berry) appointed by WIS
  • Server specifications discussed further with ITI Unix
David Watters 26-Oct-2012
Week ending 12th October 2012
  • Active Data Guard training confirmed with QA; purchase order issued
  • Resourcing issues discussed
  • Meeting with Programme Manager to decide approach to issues
  • Propsal to appoint Senior Supplier to project
David Watters 26-Oct-2012
Week ending 5th October 2012
  • Risk register completed and distributed to stakeholders for comment
  • ASTA updated with revised budget for programme report
  • Training booking - purchase order chased
  • Dev Tech discussions on virtualisation
  • Discussions held on revising current plan & milestones
David Watters 09-Oct-2012
Week ending 21st September 2012
  • Query from Director's Office re budget
  • PRICCL prepared and brief resubmitted to WIS
  • Updated brief passed by WIS

 

David Watters 02-Oct-2012
Week ending 14th September 2012

PM on leave previous two weeks:

  • Estimation meeting held and draft estimate produced
  • Training for Dev Tech and Tech Management staff arranged
  • Project wiki for documentation established

After return:

  • Estimations completed and brief finalised
  • Brief submitted to WIS
David Watters 02-Oct-2012
Week ending 24/08/12
  • Work continued on project brief with target date for submission of 31/08
  • Meetings to clarify scope held with teams across IS Apps
  • Arrangements made to organise training for staff in Dev Tech and Tech Management
  • Meetings to clarify technical solution & approach to virtualisation commenced
  • Estimation meeting arranged for 28/08
  • Arrangements for leave period made with Programme Manager
David Watters 24-Aug-2012