Report for December
- Report Date
- December 2019
Achievements in Last Period
-
Collecting applications and shortlisting applicants to Branch Manager role
-
Interviews for the Branch Manager role
Issues
- Resource across project and availability of Project Sponsor
- Reaching agreement on scope for Payroll within new service
- Reaching agreement on nature of the Administrator role
These have been escalated to Project Sponsor / CIO
Next Steps
Priorities include:
- Confirm and progress preferred payroll process
- Progress / sign off marketing / communication templates
- Progress plans for office location
- Progress sign off for terms and conditions
- Complete Branch Manager recruitment
- Commence Administrator recruitment
- Approved budget
- 20.0 days
- Activity this month
- 1.0 day
- Activity this year
- 14.0 days
- Activity to date
- 14.0 days
- Estimate to complete current year
- 8.0 days
- Estimate to complete future years
- 0.0 days