Report for September
- Report Date
- September 2019
Achievements in Last Period
-
Ongoing meetings with Payroll to identify agreed approach for new service
-
Agreement on location
Issues
- Resource across project and availability of Project Sponsor
- Reaching agreement on scope for Payroll within new service
- Delayed recruitment of Branch manager has now impacted potential go live date
- Marketing approval is outstanding
Next Steps
- Progress Payroll process
- Progress recruitment of Branch manager
- Agree draft marketing / communication templates
- Progress plans for office location
- Approved budget
- 35.0 days
- Activity this month
- 3.4 days
- Activity this year
- 7.2 days
- Activity to date
- 24.0 days
- Estimate to complete current year
- 17.8 days
- Estimate to complete future years
- 0.0 days