AP78-072 - MyEd Database Migration to Oracle 12

A compliance project to upgrade the Oracle DB to version 12c as support for the exisiting Oracle Version (11g) runs out in October 2017.

 

Project reinitiated 28/05/2018 after being suspended at WIS 30/03/2018.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2018 BLUE 60.0 days 56.4 days 0.0

Project Info

Project
MyEd Database Migration to Oracle 12
Code
ISG010
Programme
ISG Portfolio Projects (OTHISG)
Management Office
ISG PMO
Project Manager
Richard Bailey
Project Sponsor
Lisa Dawson
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
06-Nov-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
03-Aug-2018
Programme Priority
3
Overall Priority
Normal
Category
Compliance

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.