Closure Report

Project Summary

Background

The Integrated Administration Services project sat within the ISG Change Programme, which was created to focus on how staff in ISG work together and how services are delivered, enabling everyone in ISG to play their part in taking the service forward and making it fit for the future. The ISG Change Programme is focusing on nine key themes, one of which is Working Together.

The purpose of the Working Together theme is two-fold:

  • to have flexible, innovative and attractive working environments across the whole of IS, where Divisions, Teams and staff can interact and collaborate freely irrespective of their physical location
  • to create flexibility in both how and where we work; and to make more effective and efficient use of our time through improved processes and business tools

The Integrated Administration Services project was part of the Working Together theme.

Scope

The scope of the project extended to administrative services provided by Directorate administration staff that used processes and forms owned solely by Information Services. The project did not look to change University wide processes or enterprise systems (e.g. those owned by Central Finance and Central HR). Nor did it include Facilities tasks such as post, store room, Project support administration tasks and other non-central admin tasks such as AV bookings, switchboard. These will be reviewed at a later date.

Business Objectives

The primary objective of the project was the launch of a well-articulated, integrated, effective and efficient administration service.  An integrated team, the Business Admin team, was launched on 27 March 2018 and since then, a number of changes have been introduced to the team’s administrative processes that will make the team more effective and efficient in the future.

Deliverables

Delivered

  • Administration Service identity

27 Mar 18

  • Staff composition and structure of Administration Service

22 Mar 18

  • Launch of new Administration Service

27 Mar 18

  • Clear roles and responsibilities (organisation chart)

22 Mar 18

  • All admin staff have up to date, consistent Job Descriptions

27 Mar 18

  • Clear career pathways and professional development opportunities for admin staff

Ongoing

  • Review of admin processes, forms and practices

29 Sep 17

  • Implement standardised and efficient (within constraints) admin processes, forms and practices

21 Jun 18

  • Design & implementation of interim and/or final workflow structure

25 Apr 18

  • Methodology for creation of knowledge base

25 Apr 18

  • Service catalogue

25 Apr 18

 

Success Criteria

The Project Brief stated two success criteria:

  1. The project would be viewed as successful if all of the above deliverables were achieved. Given that only one of the deliverables above has not been achieved and is work in progress, the project can be viewed as successful with respect to this criterion.
  2. Ensure that the level of service being provided by the admin team is viewed as least as good, if not better than before it was integrated.

It is too early to determine whether this is the case. The team is still getting used to the new ways of working and is also not at full resource capacity, so there has been a drop in the level of service being provided, as anticipated. It is proposed that the following customer satisfaction surveys should be undertaken:

December 2018 – target of 65% customer satisfaction

March 2019 – target of 75% customer satisfaction

July 2019 – target of 85% customer satisfaction

 

Benefits

By implementing an integrated administration service, the following benefits are expected to be delivered:

  • flexibility of admin resource to better manage workload
  • removal of duplication of effort
  • reduction in vulnerability of small admin cohorts
  • greater flexibility for managing peaks and troughs
  • efficiency gains from improved processes
  • admin staff have developed their knowledge and skills base
  • the rest of the University finds it easier to interface and communicate with ISG

These benefits will be measured as follows:

Benefit

Measure

Target

Baseline date

Review date

User satisfaction rating

Survey of UniDesk and other users

65%

75%

85%

N/a

31 Dec 2018

31 Mar 2019

31 Jul 2019

Admin team satisfaction rating

Survey of admin team members

60%

1 Oct 2018

31 Mar 2019

Standardised Finance processes operating across all Directorates

Number of standardised processes in place

8/8

1 July 2018

31 Mar 2019

More timely completion for raising POs

No. of follow-ups on calls

50% reduction

1 Oct 2018

31 Mar 2019

More timely completion for paying contractor invoices

No. of approved contractor invoices paid within 5 working days

100%

1 Oct 2018

31 Mar 2019

Standardised HR processes operating across all Directorates

Number of standardised processes in place

6/6

1 July 2018

31 Mar 2019

User satisfaction rating for staff recruitment

Survey of users

85%

1 Oct 2018

31 Jul 2019

Options produced for Secretary Service

Completed/Not completed

Completed

N/A

31 Mar 2019

Support levels for Committees & Groups agreed

Completed/Not completed

Completed

N/A

31 Mar 2019

Provided support for at least one additional event by end March 2019

Completed/Not completed

Completed

N/A

31 Mar 2019

 

Analysis of Resource Usage:

N/A

 

Key Learning Points

Confidentiality of information on UniDesk is an issue: information in the Business Admin team’s queue can be viewed by all the University of Edinburgh’s UniDesk operators. Given that the admin team are handling personal information about absence, contractor rates and candidates for new posts, this led to additional steps in some of the processes with information needing to be submitted through SharePoint and then being manipulated once in UniDesk. The perception by some members of the team is that the new ways of working are more onerous than before, because of these extra steps.

SharePoint has proved to be a very useful tool, enabling us to create complex forms that couldn’t be created on UniDesk. This has helped to improve the quality of the data provided to the Business Admin team, reducing the amount of time spent chasing for users for accurate information.

Outstanding Issues

In addition to the outstanding deliverable and non-measurement of success described in Project Summary, there were two project milestones that have not been completed. This was due to other priorities and commitments, two project milestones have not been completed. The consultation process also identified the need for a further review of the Grade 6 job description and a potential impact on the Grade 7 job description caused by the introduction of the new IS Finance roles.

Completion of all these activities has been moved to Business As Usual.

Milestone/Deliverables

Original Target Date

Notes

Revised Target Date

Phase 1 Service Options sign offs (Travel, Diary Management/Secretary)

31 May 2018

Travel proposal ready for SMT approval

Travel: 4 Sep 2018

Diary: 4 Sep 2018

Phase 2 Service Option sign offs (Committee/Group Support, Event Management)

6 July 2018

Committee/Group Support proposal ready for SMT approval

Committee: 4 Sep 2018

Event: 4 Sep 2018

Clear career pathways and professional development opportunities for admin staff

 

 

30 Nov 2018

Ensure that the level of service being provided by the admin team is viewed as least as good, if not better than before it was integrated.

 

 

31 Jul 2019

Grade 6 Job Description

 

 

31 Aug 2018

Grade 7 Job Description

 

 

30 Sep 2018

 

Project Info

Project
Integrated Administration Services
Code
ISG004
Programme
IS Change - Working Together (CWT)
Management Office
ISG PMO
Project Manager
Rhona Mcmorland
Project Sponsor
Alistair Fenemore
Current Stage
Close
Status
Closed
Start Date
30-Jan-2017
Planning Date
n/a
Delivery Date
27-Jul-2018
Close Date
08-Aug-2018
Overall Priority
Higher
Category
Discretionary

Documentation

Close