January 2020 Monthly Project Report - WIP
- Report Date
- January 2020
Achievements
- Progressing Nexus in TEST
- Meeting with project sponsor to agree sequence of Development tools upgrades plans
- Project Sponsor reviewing budgets and when tools may be upgraded
- Replan development tools upgrades as agreed
- Started progressing P2 to migrate puppet master 4 to puppet master 5, however if it cannot be completed before mid Feb it will be restarted after SAC080 work has completed
- Dates to be agreed
Issues
- No issues
Next Steps
- Meeting with project sponsor to agree sequence of Development tools upgrades plans
- Replan development tools upgrades as agreed
- Started progressing P2 to migrate puppet master 4 to puppet master 5, however if it cannot be completed before mid Feb it will be restarted after SAC080 work has completed
- Dates to be agreed as SAC080 is also dependent upon SAC083 the SITS Double upgrade
| Stage | Milestone | Due Date |
| Execute | P2- Migrate puppet master 4 to puppet master 5 | 17-Feb-2020 |
| Execute | P3 Puppet - test and fix puppet master 5 | 04-Mar-2020 |
| Deliver | P3 Puppet library code master 5 delivered | 19-Mar-2020 |
| Execute | Python Acceptance Tested | 27-Mar-2020 |
| Deliver | Python Delivered | 08-Apr-2020 |
| Deliver | Oracle Grid Delivered | 21-May-2020 |
| Execute | Bamboo Acceptance Tested | 29-May-2020 |
| Deliver | Bamboo Delivered | 11-Jun-2020 |
| Execute | Nexus Updated | 16-Jun-2020 |
| Deliver | Nexus Delivered | 25-Jun-2020 |
| Execute | Overall Acceptance Milestone | 02-Jul-2020 |
| Deliver | Overall Deployment Signoff | 24-Jul-2020 |
| Close | Close | 31-Jul-2020 |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days