December 2019 Monthly Project Report
- Report Date
- December 2019
Achievements
- Completed Sentry upgrade
- Delivered Sentry upgrade
Issues
- No issues
Next Steps
- Meeting with project sponsor to agree sequence of Development tools upgrades plans
- Replan development tools upgrades as agreed
- P2 to migrate puppet master 4 to puppet master 5 is likely to start early this year
- Dates to be agreed
Green RAG status this month
Milestones
| Stage | Milestone | Due Date |
| Execute | P2- Migrate puppet master 4 to puppet master 5 | 17-Feb-2020 |
| Execute | P3 Puppet - test and fix puppet master 5 | 04-Mar-2020 |
| Deliver | P3 Puppet library code master 5 delivered | 19-Mar-2020 |
| Execute | Python Acceptance Tested | 27-Mar-2020 |
| Deliver | Python Delivered | 08-Apr-2020 |
| Deliver | Oracle Grid Delivered | 21-May-2020 |
| Execute | Bamboo Acceptance Tested | 29-May-2020 |
| Deliver | Bamboo Delivered | 11-Jun-2020 |
| Execute | Nexus Updated | 16-Jun-2020 |
| Deliver | Nexus Delivered | 25-Jun-2020 |
| Execute | Overall Acceptance Milestone | 02-Jul-2020 |
| Deliver | Overall Deployment Signoff | 24-Jul-2020 |
| Close | Close | 31-Jul-2020 |
- Approved budget
- 155.0 days
- Activity this month
- 3.0 days
- Activity this year
- 21.0 days
- Activity to date
- 21.0 days
- Estimate to complete current year
- 134.0 days
- Estimate to complete future years
- 0.0 days