Report for October 2019
- Report Date
- October 2019
Achievements in Last Period
- Project Management handed over from Maurice Franceschi to Tim Gray
- EdWeb successfully deployed to LIVE
- DEV environments for CAM, Blogs and MGen applications successfully migrated over to Maria DB
- TEST environments successfully migrated over to Maria DB for CAM, Blogs and MGen applications
- UAT started on CAM, Blogs and MGen
- Comms to CAM, Blogs and MGen applications' users ongoing
- Dates for LIVE migration for CAM, Blogs and MGen applications agreed
Issues/Risk
- Several issues,/after work remain must be completed on EdWeb before the Deployment review can be signed off. One of these issues, with the master/slave configuration after the EdWeb deployment resulted in the postponement of the EdWeb monthly module update. This issue has now been fixed.
Next Steps
- Complete outstanding issues with EdWeb
- Migrate TRAIN environment for Edweb
- Continue with comms to CAM, Blogs and MGen applications' users
- Start planning the remaining work
Milestones
| EdWeb Deployed to Live - DSOR | 09-Oct-2019 |
| CAM BLOGS MGEN migrated to Maria DB on DEV | 10-Oct-2019 |
| CAM BLOGS MGEN migrated to Maria DB on TEST | 17-Oct-2019 |
| CAM BLOGS MGEN migrated to Maria DB on LIVE | 24-Oct-2019 |
| DSOR for CAM, BLOGS, MGEN | 31-Oct-2019 |
| Project Close | 15-Dec-2019 |
- Approved budget
- 100.0 days
- Activity this month
- 21.0 days
- Activity this year
- 36.0 days
- Activity to date
- 115.0 days
- Estimate to complete current year
- 43.0 days
- Estimate to complete future years
- 0.0 days