Report for October 2019

Report Date
October 2019

Achievements in Last Period

  • Project Management handed over from Maurice Franceschi to Tim Gray
  • EdWeb successfully deployed to LIVE
  • DEV environments for CAM, Blogs and MGen applications successfully migrated over to Maria DB
  • TEST environments successfully migrated over  to Maria DB for CAM, Blogs and MGen applications 
  • UAT started on CAM, Blogs and MGen
  • Comms to CAM, Blogs and MGen applications' users ongoing
  • Dates for LIVE migration for CAM, Blogs and MGen applications agreed

Issues/Risk

  • Several issues,/after work remain must be completed on EdWeb before the Deployment review can be signed off. One of these issues, with the master/slave configuration after the EdWeb deployment resulted in the postponement of the EdWeb monthly module update. This issue has now been fixed. 

Next Steps

  • Complete outstanding issues with EdWeb
  • Migrate TRAIN environment for Edweb
  • Continue with comms to CAM, Blogs and MGen applications' users
  • Start planning the remaining work

Milestones

 

EdWeb Deployed to Live - DSOR 09-Oct-2019
CAM BLOGS MGEN migrated to Maria DB on DEV 10-Oct-2019
CAM BLOGS MGEN migrated to Maria DB on TEST 17-Oct-2019
CAM BLOGS MGEN migrated to Maria DB on LIVE 24-Oct-2019
DSOR for CAM, BLOGS, MGEN 31-Oct-2019
Project Close 15-Dec-2019

 

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
100.0 days
Activity this month
21.0 days
Activity this year
36.0 days
Activity to date
115.0 days
Estimate to complete current year
43.0 days
Estimate to complete future years
0.0 days

Project Info

Project
MySQL Environment Migration
Code
INF143
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Stefan Kaempf
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
08-Oct-2018
Planning Date
14-Nov-2018
Delivery Date
10-Dec-2019
Close Date
31-Jan-2020
Programme Priority
4
Overall Priority
Highest
Category
Compliance

Documentation