Monthly Project Report
- Report Date
- September 2018
Achievements :
- Project milestones reviewed
- All project TADs completed
- WebPA to Go Live planned for 3-Oct
- Planned decommission Lamp Servers in Dev, Test and Live after WebPA is Live
- Closure to be drafted ready for closure after WebPA is live
Issues
- None
Next Steps :
- WebPA to Go Live
- Decommission Lamp Servers in Dev, Test and Live
- Closure to be completed
RAG Status of Green
Milestones :
| Date | Milestone |
| 5-Oct-2018 | Deploy Migrated Applications |
| 12-Oct-2018 | Deployment Review and Close |
- Approved budget
- 119.0 days
- Activity this month
- 8.0 days
- Activity this year
- 21.0 days
- Activity to date
- 117.0 days
- Estimate to complete current year
- 6.0 days
- Estimate to complete future years
- 0.0 days