Monthly Project Report

Report Date
September 2018

Achievements :

  • Project milestones reviewed
  • All project TADs completed
  • WebPA to Go Live planned for 3-Oct
  • Planned decommission Lamp Servers in Dev, Test and Live after WebPA is Live
  • Closure to be drafted ready for closure after WebPA is live

Issues

  • None

Next Steps :

  • WebPA to Go Live
  • Decommission Lamp Servers in Dev, Test and Live
  • Closure to be completed

RAG Status of Green

Milestones :

Date Milestone
5-Oct-2018 Deploy Migrated Applications
12-Oct-2018 Deployment Review and Close
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
119.0 days
Activity this month
8.0 days
Activity this year
21.0 days
Activity to date
117.0 days
Estimate to complete current year
6.0 days
Estimate to complete future years
0.0 days

Project Info

Project
LAMP / WIMP Platform Upgrade
Code
INF127
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
09-Aug-2017
Planning Date
21-Sep-2017
Delivery Date
05-Oct-2018
Close Date
12-Oct-2018
Programme Priority
3
Overall Priority
Normal
Category
Compliance