Monthly Project Report

Report Date
August 2018

 

Achievements :

  • Talks and Talks Reminder went live Aug 14th
  • WebPA completed in DEV
  • DRPS to be tested
  • DRPS went Live Aug 15th
  • WebPA completed in TEST and signed off ready to go live after the change freeze 30-Aug (23-Aug)
  • Closure to be started
  • Completed the last acceptance test of the other migrated applications (WebPA)
  • Delay to deploying WebPA the day before the change freeze

Issues

  • None

Next Steps :

  • Project milestones to be revised
  • Project TADs to be completed
  • WebPA to Go Live after the change freeze at the start of October
  • Decommission Lamp Servers in Dev, Test and Live  after WebPA is Live
  • Closure to be drafted ready for closure after WebPA is live

RAG Status of Amber

Milestones :

Date Milestone
5-Oct-2018 Deploy Migrated Applications
12-Oct-2018 Deployment Review and Close
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
119.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
LAMP / WIMP Platform Upgrade
Code
INF127
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
09-Aug-2017
Planning Date
21-Sep-2017
Delivery Date
05-Oct-2018
Close Date
12-Oct-2018
Programme Priority
3
Overall Priority
Normal
Category
Compliance