Monthly Project Report
- Report Date
- August 2018
Achievements :
- Talks and Talks Reminder went live Aug 14th
- WebPA completed in DEV
- DRPS to be tested
- DRPS went Live Aug 15th
- WebPA completed in TEST and signed off ready to go live after the change freeze 30-Aug (23-Aug)
- Closure to be started
- Completed the last acceptance test of the other migrated applications (WebPA)
- Delay to deploying WebPA the day before the change freeze
Issues
- None
Next Steps :
- Project milestones to be revised
- Project TADs to be completed
- WebPA to Go Live after the change freeze at the start of October
- Decommission Lamp Servers in Dev, Test and Live after WebPA is Live
- Closure to be drafted ready for closure after WebPA is live
RAG Status of Amber
Milestones :
| Date | Milestone |
| 5-Oct-2018 | Deploy Migrated Applications |
| 12-Oct-2018 | Deployment Review and Close |
- Approved budget
- 119.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days