January 2017
- Report Date
- January 2017
Achievements this Period
- Sign off achieved for News DEV environment
- TEST environment complete and data migrated. All issues in TEST have been resolved.
- Production Management currently performing testing on News applications. HRMI, SPACEMART, TELSMI, LYNDAMI all passed ok. Need results from ADMISMI, ORGMI, STUDMI, EFINARCH
- Agreement made that GEN migration will commence in April through to July.
Issues
-
UNIDESKMI testing has uncovered a problem in running the extract, but noted that it is not 12c related as did not work in 11c.
-
Cost is RED as the project costs are likely to exceed 20% of the original budget. This is a prediction on where we are now with the NEWS migration, and what's left to complete. Estimation meeting is on 10th Feb for GEN and Programme Manager and Sponsor will be made aware of the budget required.
Next Steps
- GEN re-estimation (meeting on Friday 10th Feb)
- Sign off NEWS integration and UAT.
- Schedule in a go live date for NEWS.
- Resource for GEN migration from April, and re-plan the milestones after the estimation meeting.
Milestones
03-Feb-2017 | NewsTEST Integration Sign off |
14-Feb-2017 | NewsTEST Acceptance sign off |
17-Feb-2017 | Live environment build for NewsLive complete |
28-Feb-2017 | NewsLive deploy to LIVE |
15-Mar-2017 | NewsLive Deployment sign off |
14-Apr-2017 | DEV environment build for GenDEV complete |
28-Apr-2017 | GenDEV Build sign off |
- Approved budget
- 197.0 days
- Activity this month
- 12.0 days
- Activity this year
- 71.0 days
- Activity to date
- 78.0 days
- Estimate to complete current year
- 49.0 days
- Estimate to complete future years
- 81.0 days