December 2016

Report Date
December 2016

Achievements this Period

Issues

  • NewsLIVE deployment and sign off milestone will need to be re-planned in accordance with Dev Tech and Applications Management timescales
  • Time is AMBER as we still need to build the LIVE environment for the deployment.

Next Steps

  • Build LIVE environment for NewsLIVE
  • Schedule in a go live date
  • Re-estimate the time needed for GenDEV to GenLIVE migration
  • Begin GenDEV environment set up

 

18-Jan-2017 NewsLive deploy to LIVE
01-Feb-2017 NewsLive Deployment sign off
31-Jan-2017 Re-estimation for GenLive
03-Feb-2017 DEV environment build for GenDEV complete
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
197.0 days
Activity this month
7.5 days
Activity this year
59.0 days
Activity to date
66.0 days
Estimate to complete current year
56.0 days
Estimate to complete future years
81.0 days

Project Info

Project
Migrate core databases to Oracle 12c
Code
INF121
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
06-Apr-2016
Planning Date
26-Aug-2016
Delivery Date
04-Dec-2018
Close Date
11-Apr-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance