December 2016
- Report Date
- December 2016
Achievements this Period
- Issues on DEV now fixed.
- Migration to TEST complete
- Applications Management have tested and have passed all NewsTEST applications.
- Results have been updated in the wiki page - https://www.wiki.ed.ac.uk/pages/viewpage.action?pageId=325461127
Issues
- NewsLIVE deployment and sign off milestone will need to be re-planned in accordance with Dev Tech and Applications Management timescales
- Time is AMBER as we still need to build the LIVE environment for the deployment.
Next Steps
- Build LIVE environment for NewsLIVE
- Schedule in a go live date
- Re-estimate the time needed for GenDEV to GenLIVE migration
- Begin GenDEV environment set up
18-Jan-2017 | NewsLive deploy to LIVE |
01-Feb-2017 | NewsLive Deployment sign off |
31-Jan-2017 | Re-estimation for GenLive |
03-Feb-2017 | DEV environment build for GenDEV complete |
- Approved budget
- 197.0 days
- Activity this month
- 7.5 days
- Activity this year
- 59.0 days
- Activity to date
- 66.0 days
- Estimate to complete current year
- 56.0 days
- Estimate to complete future years
- 81.0 days