November 2016
- Report Date
- November 2016
Achievements this Period
- TEST environment for NEWDev set up
- Testing carried out on post NEWSDev migrated applications. Results are in the wiki page - https://www.wiki.ed.ac.uk/pages/viewpage.action?pageId=325461127
Issues
- ADMISMI, ORGMI and STUDMI has got issues to resolve in DEV after they were migrated. This is currently being worked on, and could be a privilege issue. JIRAs 2 and 3 have been raised.
- Project is AMBER as more time has been taken to fix the issues above in DEV, resulting in milestone moves.
Next Steps
- Fix issues on DEV prior to migrating to TEST
- Milestone dates to be reviewed once the fix is in DEV, but will probably move out by two weeks.
- Migrate data to TEST
- Applications Management to peer test
Milestones
25-Nov-2016 | Build sign off for NewsDEV |
01-Dec-2016 | NewsTEST Integration Sign off |
16-Dec-2016 | NewsTEST Acceptance sign off |
22-Dec-2016 | Live environment build for NewsLive complete |
11-Jan-2017 | NewsLive deploy to LIVE |
- Approved budget
- 197.0 days
- Activity this month
- 18.0 days
- Activity this year
- 50.0 days
- Activity to date
- 56.0 days
- Estimate to complete current year
- 65.0 days
- Estimate to complete future years
- 81.0 days