November 2016

Report Date
November 2016

Achievements this Period

 

Issues

  • ADMISMI, ORGMI and STUDMI has got issues to resolve in DEV after they were migrated. This is currently being worked on, and could be a privilege issue. JIRAs 2 and 3 have been raised.
  • Project is AMBER as more time has been taken to fix the issues above in DEV, resulting in milestone moves.

 

Next Steps

  • Fix issues on DEV prior to migrating to TEST
  • Milestone dates to be reviewed once the fix is in DEV, but will probably move out by two weeks.
  • Migrate data to TEST
  • Applications Management to peer test

 

Milestones

25-Nov-2016 Build sign off for NewsDEV
01-Dec-2016 NewsTEST Integration Sign off
16-Dec-2016 NewsTEST Acceptance sign off
22-Dec-2016 Live environment build for NewsLive complete
11-Jan-2017 NewsLive deploy to LIVE
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
197.0 days
Activity this month
18.0 days
Activity this year
50.0 days
Activity to date
56.0 days
Estimate to complete current year
65.0 days
Estimate to complete future years
81.0 days

Project Info

Project
Migrate core databases to Oracle 12c
Code
INF121
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
06-Apr-2016
Planning Date
26-Aug-2016
Delivery Date
04-Dec-2018
Close Date
11-Apr-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance