Report for December 2018

Report Date
December 2018

Achievements this Period

  • Migrations completed to new LIVE environment
  • User checks completed
  • Bamboo checks finalised

Issues

  • Extra effort required - to be drawn from Programme contingency

Next Period

  • APPS LIVE environment to be 'tidied'
  • Project closure

 

Milestones

Stage Milestone Due Date
Deliver AppsLive deployment sign off 17-Jan-2019
Close Closure 25-Jan-2019
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
Within Tolerance
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
501.0 days
Activity this month
19.4 days
Activity this year
129.5 days
Activity to date
508.2 days
Estimate to complete current year
9.1 days
Estimate to complete future years
0.0 days

Project Info

Project
Migrate core databases to Oracle 12c
Code
INF121
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
06-Apr-2016
Planning Date
26-Aug-2016
Delivery Date
04-Dec-2018
Close Date
11-Apr-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance