Report for December 2018
- Report Date
- December 2018
Achievements this Period
- Migrations completed to new LIVE environment
- User checks completed
- Bamboo checks finalised
Issues
- Extra effort required - to be drawn from Programme contingency
Next Period
- APPS LIVE environment to be 'tidied'
- Project closure
Milestones
Stage | Milestone | Due Date |
---|---|---|
Deliver | AppsLive deployment sign off | 17-Jan-2019 |
Close | Closure | 25-Jan-2019 |
- Approved budget
- 501.0 days
- Activity this month
- 19.4 days
- Activity this year
- 129.5 days
- Activity to date
- 508.2 days
- Estimate to complete current year
- 9.1 days
- Estimate to complete future years
- 0.0 days