Report for October 2018
- Report Date
- October 2018
Achievements this Period
- Migrations completed to new DEV environment
- Post-migration checks completed
- APPS TEST environment created
- Further planning for TEST & LIVE approved
Issues
- Post-migration checks took longer than anticipated
Next Period
- UAT to start
- Post-migration checks to be completed
- Bamboo checks to be finalised
- APPS LIVE environment to be established
Milestones
Stage | Milestone | Due Date |
---|---|---|
Integrate | AppsTEST integration sign off | 12-Nov-2018 |
Accept | AppsTEST Acceptance sign off | 26-Nov-2018 |
Deliver | Live environment build for AppsLive complete | 30-Nov-2018 |
Deliver | AppsLive deploy to LIVE | 04-Dec-2018 |
Deliver | AppsLive deployment sign off | 17-Dec-2018 |
Close | Closure | 25-Jan-2019 |
- Approved budget
- 473.0 days
- Activity this month
- 37.2 days
- Activity this year
- 72.8 days
- Activity to date
- 451.4 days
- Estimate to complete current year
- 28.3 days
- Estimate to complete future years
- 0.0 days