Report for October 2018

Report Date
October 2018

Achievements this Period

  • Migrations completed to new DEV environment
  • Post-migration checks completed
  • APPS TEST environment created
  • Further planning for TEST & LIVE approved

Issues

  • Post-migration checks took longer than anticipated

Next Period

  • UAT to start
  • Post-migration checks to be completed
  • Bamboo checks to be finalised
  • APPS LIVE environment to be established

 

Milestones

Stage Milestone Due Date
Integrate AppsTEST integration sign off 12-Nov-2018
Accept AppsTEST Acceptance sign off 26-Nov-2018
Deliver Live environment build for AppsLive complete 30-Nov-2018
Deliver AppsLive deploy to LIVE 04-Dec-2018
Deliver AppsLive deployment sign off 17-Dec-2018
Close Closure 25-Jan-2019
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
473.0 days
Activity this month
37.2 days
Activity this year
72.8 days
Activity to date
451.4 days
Estimate to complete current year
28.3 days
Estimate to complete future years
0.0 days

Project Info

Project
Migrate core databases to Oracle 12c
Code
INF121
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
06-Apr-2016
Planning Date
26-Aug-2016
Delivery Date
04-Dec-2018
Close Date
11-Apr-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance