Report for September 2018

Report Date
September 2018

Achievements this Period

  • APPS DEV environment created
  • Migrations started to new environment
  • Pre-migration checks executed
  • Post-migration checks started

Issues

  • Post-migration checks may take longer than anticipated
  • Remaining milestones to be reviewed and agreed

 

Next Period

  • Post-migration checks to be completed
  • APPS TEST environment to be established
  • Migrations to TEST
  • UAT to start

 

Milestones

05-Oct-2018 Test environment build for AppsTEST complete
26-Oct-2018 AppsTEST integration sign off
09-Nov-2018 AppsTEST Acceptance sign off
23-Nov-2018 Live environment build for AppsLive complete
04-Dec-2018 AppsLive deploy to LIVE
17-Dec-2018 AppsLive deployment sign off
25-Jan-2019 Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
465.0 days
Activity this month
28.6 days
Activity this year
35.0 days
Activity to date
413.0 days
Estimate to complete current year
67.8 days

Project Info

Project
Migrate core databases to Oracle 12c
Code
INF121
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
06-Apr-2016
Planning Date
26-Aug-2016
Delivery Date
04-Dec-2018
Close Date
11-Apr-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance