Report for September 2018
- Report Date
- September 2018
Achievements this Period
- APPS DEV environment created
- Migrations started to new environment
- Pre-migration checks executed
- Post-migration checks started
Issues
- Post-migration checks may take longer than anticipated
- Remaining milestones to be reviewed and agreed
Next Period
- Post-migration checks to be completed
- APPS TEST environment to be established
- Migrations to TEST
- UAT to start
Milestones
05-Oct-2018 | Test environment build for AppsTEST complete |
26-Oct-2018 | AppsTEST integration sign off |
09-Nov-2018 | AppsTEST Acceptance sign off |
23-Nov-2018 | Live environment build for AppsLive complete |
04-Dec-2018 | AppsLive deploy to LIVE |
17-Dec-2018 | AppsLive deployment sign off |
25-Jan-2019 | Closure |
- Approved budget
- 465.0 days
- Activity this month
- 28.6 days
- Activity this year
- 35.0 days
- Activity to date
- 413.0 days
- Estimate to complete current year
- 67.8 days