Report for February 2018
- Report Date
- February 2018
Achievements this Period
- GEN migration to LIVE completed
Issues
- None
Next Steps
- NEWS remigration to Oracle 12.2
- Decommission old NEWS and GEN databases
- Lessons learned report on GEN to be written and used for APPS
- Suspend project
Milestones
07-Mar-2018 | NewsDEV migrate to Oracle 12.2 |
22-Mar-2018 | NewsTEST migrate to Oracle 12.2 |
30-Mar-2018 | NewsTEST UAT complete |
03-Apr-2018 | NewsLIVE migrate to Oracle12.2 |
- Approved budget
- 439.0 days
- Activity this month
- 15.0 days
- Activity this year
- 139.0 days
- Activity to date
- 345.0 days
- Estimate to complete current year
- 14.0 days
- Estimate to complete future years
- 100.0 days