Report for February 2018

Report Date
February 2018

Achievements this Period

  • GEN migration to LIVE completed

Issues

  • None

Next Steps

  • NEWS remigration to Oracle 12.2
  • Decommission old NEWS and GEN databases
  • Lessons learned report on GEN to be written and used for APPS
  • Suspend project

 

Milestones

07-Mar-2018 NewsDEV migrate to Oracle 12.2
22-Mar-2018 NewsTEST migrate to Oracle 12.2
30-Mar-2018 NewsTEST UAT complete
03-Apr-2018 NewsLIVE migrate to Oracle12.2
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
439.0 days
Activity this month
15.0 days
Activity this year
139.0 days
Activity to date
345.0 days
Estimate to complete current year
14.0 days
Estimate to complete future years
100.0 days

Project Info

Project
Migrate core databases to Oracle 12c
Code
INF121
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
06-Apr-2016
Planning Date
26-Aug-2016
Delivery Date
04-Dec-2018
Close Date
11-Apr-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance