July 2016

Report Date
July 2016

Achievements this Period

  • Brief completed with estimate

 

Issues

  • Planning milestone needs to be moved as sponsor is on annual leave and budget cannot be approved. Project is RED again as a result of this.

 

Next Steps

  • Brief signed off and budget approved
  • Book Dev Tech to start in September

 

Milestones

26-Aug-2016Planning sign off
16-Sep-2016Systems Analysis and design complete
14-Oct-2016Build - APPSLive
21-Oct-2016Build - NEWSLive
04-Nov-2016Build GENLive
08-Nov-2016Build Sign off
16-Nov-2016Integration - Test Environments Built
23-Nov-2016Integration - APPSLive migrated
01-Dec-2016Integration - GENLive migrated
06-Dec-2016Integration - NEWSLive migrated
21-Dec-2016Integration sign off review
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Migrate core databases to Oracle 12c
Code
INF121
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
06-Apr-2016
Planning Date
26-Aug-2016
Delivery Date
04-Dec-2018
Close Date
11-Apr-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance