July 2016
- Report Date
- July 2016
Achievements this Period
- Brief completed with estimate
Issues
- Planning milestone needs to be moved as sponsor is on annual leave and budget cannot be approved. Project is RED again as a result of this.
Next Steps
- Brief signed off and budget approved
- Book Dev Tech to start in September
Milestones
26-Aug-2016 | Planning sign off |
16-Sep-2016 | Systems Analysis and design complete |
14-Oct-2016 | Build - APPSLive |
21-Oct-2016 | Build - NEWSLive |
04-Nov-2016 | Build GENLive |
08-Nov-2016 | Build Sign off |
16-Nov-2016 | Integration - Test Environments Built |
23-Nov-2016 | Integration - APPSLive migrated |
01-Dec-2016 | Integration - GENLive migrated |
06-Dec-2016 | Integration - NEWSLive migrated |
21-Dec-2016 | Integration sign off review |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days