Report for October 2017
- Report Date
- October 2017
Achievements this Period
- Decision made to alter the "SQLNET.ORA” to “ALLOWED_LOGON_VERSION_SERVER = 8” which will allow us to proceed with migrating GEN Dev to GEN TEST. This decision will also apply to the APPS migrations, which contain a number for ColdFusion 10 applications.
- Project milestones have been replanned, and resource secured. This has been approved.
- Three technical issues with GEN which had been raised in JIRA have been resolved.
Issues
- There will be a budget review in November to determine the number of extra days required to complete the project.
Next Steps
- GEN to be migrated into TEST
- Integration testing to commence
- LIVE environment to be upgraded to 12.2 ahead of the planned migrations. The only application on LIVE is Bamboo.
- Review required of the Bamboo plans to determine if any of them require to be approved and enabled for the GEN applications.
Milestones
10-Nov-2017 | GENDEV Post-migration Checks |
15-Dec-2017 | GenTEST post migration (integration) sign off |
17-Jan-2018 | GenTEST Acceptance sign off |
19-Jan-2018 | Re-estimation for AppsLive |
30-Jan-2018 | GenLive deploy to LIVE |
14-Feb-2018 | GenLive deployment sign off |
02-Mar-2018 | AppsDEV build sign off |
23-Mar-2018 | Test environment build for AppsTEST complete |
04-Apr-2018 | AppsTEST integration sign off |
20-Apr-2018 | AppsTEST Acceptance sign off |
07-May-2018 | Live environment build for AppsLive complete |
15-May-2018 | AppsLive deploy to LIVE |
31-May-2018 | AppsLive deployment sign off |
15-Jun-2018 | Closure |
- Approved budget
- 81.0 days
- Activity this month
- 12.0 days
- Activity this year
- 65.0 days
- Activity to date
- 271.0 days
- Estimate to complete current year
- 115.0 days
- Estimate to complete future years
- 0.0 days