Report for September 2017

Report Date
September 2017

Achievements this Period

  • A meeting on the CF10 / Oracle 12.2 support  with Production Management, Development Technology was held.  There is one feasible options provided by Production is that we could create a separate environment for CF10 running on Oracle 11g.

 

Issues

  • Upgrading to CF11 is too big and out of scope of this project. The project would need to be suspended until any upgrade is planned in another project and completed.
  • Lowering the “SQLNET.ORA” to “ALLOWED_LOGON_VERSION_SERVER = 8” has been discounted as an option. This would affect all applications on the server, and also moving forward it would not be as simple as raising it again as all applications would need to be tested.
  • APPS migrations would be affected by this issue.
  • Project is currently 50 days over budget, and this will increase as GEN needs to be fully resourced when the  CF / Oracle issue is resolved.

 

Next Steps

  • Pm to get an agreement on a viable option for the CF10 / Oracle 12.2 issue that is suitable for everyone. Currently this looks to be creating a separate environment to host CF10 applications running on Oracle 11g.
  • Meeting to be scheduled W/C 16th October as a number of the project team are on annual leave until then.
Project Status
RAG Status
Time
RED
Cost
RED
Scope
GREEN
Overall
RED
RAG Commentary
Issue. Cannot proceed to TEST as ColdFusion 10 is unsupported by Oracle 12.2 and the migration causes errors. PM to arrange a meeting to discuss the options we have, one of which is to put all CF10 applications onto their own CF10 / Oracle 11g environment.
Change Status
Activity
Approved budget
81.0 days
Activity this month
24.0 days
Activity this year
52.0 days
Activity to date
207.0 days
Estimate to complete current year
77.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Migrate core databases to Oracle 12c
Code
INF121
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
06-Apr-2016
Planning Date
26-Aug-2016
Delivery Date
04-Dec-2018
Close Date
11-Apr-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance