Report for August 2017
- Report Date
- August 2017
Achievements this Period
- Post Dev migration testing complete with some issues found and mostly resolved.
- Review of APPS migrations started, and start of environment build while waiting for testing to complete.
Issues
- Milestones for remaining GEN will not be met and to be reviewed with the team.
- Issues encountered with CALMAC and Insurance applications that require a security setting to be altered. An assessment will be carried out by Dev Tech on the security implication of lowering to this level and the risk will be reviewed at WIS.
- Applications running on ColdFusion 10 and 11 are not supported or able to connect the Oracle 12.2 pluggable database. Development resource will review and the outcome will be reviewed at WIS
- Extra budget is required as work is on-going with GEN in 17/18 which was anticipated to have been completed in 16/17.
Next Steps
- Milestones to end of GEN to be planned
- All issues to be resolved with GEN and migrate to TEST
- Integration completed and UAT started
Milestones
11-Aug-2017 | GenTEST post migration (integration) sign off |
25-Aug-2017 | GenTEST Acceptance sign off |
28-Aug-2017 | GenLive deploy to LIVE |
30-Aug-2017 | DEV environment build for AppsDEV complete |
06-Sep-2017 | Re-estimation for AppsLive |
11-Sep-2017 | GenLive deployment sign off |
15-Sep-2017 | AppsDEV build sign off |
22-Sep-2017 | Test environment build for AppsTEST complete |
18-Oct-2017 | AppsTEST integration sign off |
17-Nov-2017 | AppsTEST Acceptance sign off |
29-Nov-2017 | Live environment build for AppsLive complete |
06-Dec-2017 | AppsLive deploy to LIVE |
20-Dec-2017 | AppsLive deployment sign off |
19-Jan-2018 | Closure |
- Approved budget
- 306.0 days
- Activity this month
- 27.0 days
- Activity this year
- 27.0 days
- Activity to date
- 234.0 days
- Estimate to complete current year
- 100.0 days
- Estimate to complete future years
- 0.0 days