Report for July 2017
- Report Date
- July 2017
Achievements this Period
- Migration to DEV complete, and post-dev testing by applications management started
- Technical Architect resourced to continue with TEST and LIVE
Issues
- The current immediate milestones are quite challenging and are unlikely to be met.
- Furthermore, there are deployment dates in the special CAB period to minimise risk to start of term and this is unrealistic.
Next Steps
- Post Dev migration testing
- Milestones to end of GEN planned
- Migrate GEN to TEST
- UAT
- Migration to LIVE
Commentary from Programme Manager.
Accordingly setting project to RED
- The current immediate milestones are quite challenging and are unlikely to be met.
- Furthermore, there are deployment dates in the special CAB period to minimise risk to start of term, and this is unrealistic.
- The budget for next year is unlikely to be enough, as there were around 25 days in 16/17 which were not utilised
Milestones (proposed - to be approved by project)
04-Aug-2017 | GENDEV Post-migration Checks |
11-Aug-2017 | GenTEST post migration (integration) sign off |
25-Aug-2017 | GenTEST Acceptance sign off |
28-Aug-2017 | GenLive deploy to LIVE |
30-Aug-2017 | DEV environment build for AppsDEV complete |
06-Sep-2017 | Re-estimation for AppsLive |
11-Sep-2017 | GenLive deployment sign off |
15-Sep-2017 | AppsDEV build sign off |
22-Sep-2017 | Test environment build for AppsTEST complete |
18-Oct-2017 | AppsTEST integration sign off |
17-Nov-2017 | AppsTEST Acceptance sign off |
29-Nov-2017 | Live environment build for AppsLive complete |
06-Dec-2017 | AppsLive deploy to LIVE |
20-Dec-2017 | AppsLive deployment sign off |
19-Jan-2018 | Closure |
- Approved budget
- 306.0 days
- Activity this month
- 16.0 days
- Activity this year
- 196.0 days
- Activity to date
- 197.0 days
- Estimate to complete current year
- 6.0 days
- Estimate to complete future years
- 109.0 days