Report for May 2017
- Report Date
- May 2017
Achievements this Period
- ORACLE 12.2 environment template build complete
- RMANDEV build complete
- REPDEV, REPTEST build complete
Issues
- There was an issue with the 12.2 database template scripts which are being prevented from running, but this has now been resolved. It has caused some delays in to the original timescales.
- Project is AMBER as there have been milestone changes.
Next Steps
- Check on MyED channels if any need updated
- Assign developer resource to deploy bamboo changes and test
- Upgrade DEV environment to 12.2
- Data migration for GEN to commence to DEV
- Post migration testing for DEV
Milestones
13-Jun-2017 | Upgrade Oracle 12c GEN DEV environments to Oracle 12.2 |
16-Jun-2017 | Live environment build for GenLive complete |
21-Jun-2017 | Migrate GEN to Oracle 12.2 on DEV |
23-Jun-2017 | GENDEV Post-migration Checks |
28-Jun-2017 | GenTEST post migration (integration) sign off |
30-Jun-2017 | Upgrade REPLive |
10-Jul-2017 | Upgrade TEST and LIVE environments to Oracle 12.2 |
21-Jul-2017 | GenTEST Acceptance sign off |
26-Jul-2017 | GenLive deploy to LIVE |
- Approved budget
- 306.0 days
- Activity this month
- 17.0 days
- Activity this year
- 159.0 days
- Activity to date
- 166.0 days
- Estimate to complete current year
- 51.0 days
- Estimate to complete future years
- 90.0 days