Report for May 2017

Report Date
May 2017

Achievements this Period

  • ORACLE 12.2 environment template build complete
  • RMANDEV build complete
  • REPDEV, REPTEST build complete

Issues

  • There was an issue with the 12.2 database template scripts which are being prevented from running, but this has now been resolved. It has caused some delays in to the original timescales.
  • Project is AMBER as there have been milestone changes.

Next Steps

  • Check on MyED channels if any need updated
  • Assign developer resource to deploy bamboo changes and test
  • Upgrade DEV environment to 12.2
  • Data migration for GEN to commence to DEV
  • Post migration testing for DEV

 

Milestones

13-Jun-2017 Upgrade Oracle 12c GEN DEV environments to Oracle 12.2
16-Jun-2017 Live environment build for GenLive complete
21-Jun-2017 Migrate GEN to Oracle 12.2 on DEV
23-Jun-2017 GENDEV Post-migration Checks
28-Jun-2017 GenTEST post migration (integration) sign off
30-Jun-2017 Upgrade REPLive
10-Jul-2017 Upgrade TEST and LIVE environments to Oracle 12.2
21-Jul-2017 GenTEST Acceptance sign off
26-Jul-2017 GenLive deploy to LIVE
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
306.0 days
Activity this month
17.0 days
Activity this year
159.0 days
Activity to date
166.0 days
Estimate to complete current year
51.0 days
Estimate to complete future years
90.0 days

Project Info

Project
Migrate core databases to Oracle 12c
Code
INF121
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
06-Apr-2016
Planning Date
26-Aug-2016
Delivery Date
04-Dec-2018
Close Date
11-Apr-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance