Report for April 2017

Report Date
April 2017

Achievements this Period

  • Pre migration testing on DEV, TEST and LIVE completed
  • Project plan and estimate reviewed and agreed.
  • Error in upgrade from Oracle 12.1 to 12.2 now resolved and upgrade for RMADDEV can begin

Issues

  • There is an issue with the 12.2 database template scripts which are being prevented from running. Investigation is on-going.
  • Duration to complete the 12.2 upgrade is taking longer than anticipated. No issue with effort required, but more the duration will need extended.

Next Steps

  • Continue with GEN environment build
  • Begin DEV, TEST and LIVE Pre migration testing
  • Review of project plans and estimates for 16/17 and 17/18 will be carried out in April.

Milestones

 

05-May-2017 Oracle 12.2 GO/NO GO
12-May-2017 Upgrade Oracle 12 GEN DEV/TEST/LIVE instances to Oracle 12.2
15-May-2017 Migrate GEN to Oracle 12.2
19-May-2017 NewsLive Deployment sign off
22-May-2017 GENDEV Post-migration Checks
16-Jun-2017 GenTEST integration sign off
16-Jun-2017 Live environment build for GenLive complete
30-Jun-2017 GenTEST Acceptance sign off
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
RED
Overall
RED
RAG Commentary
Change. Resolved. Scope change to migrate to Oracle 12.2 to avoid future downtime and extended end of life. Agreed by project team and sponsor.
Change Status
Activity
Approved budget
306.0 days
Activity this month
20.0 days
Activity this year
139.0 days
Activity to date
145.0 days
Estimate to complete current year
71.0 days
Estimate to complete future years
90.0 days

Project Info

Project
Migrate core databases to Oracle 12c
Code
INF121
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
06-Apr-2016
Planning Date
26-Aug-2016
Delivery Date
04-Dec-2018
Close Date
11-Apr-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance