Report for April 2017
- Report Date
- April 2017
Achievements this Period
- Pre migration testing on DEV, TEST and LIVE completed
- Project plan and estimate reviewed and agreed.
- Error in upgrade from Oracle 12.1 to 12.2 now resolved and upgrade for RMADDEV can begin
Issues
- There is an issue with the 12.2 database template scripts which are being prevented from running. Investigation is on-going.
- Duration to complete the 12.2 upgrade is taking longer than anticipated. No issue with effort required, but more the duration will need extended.
Next Steps
- Continue with GEN environment build
- Begin DEV, TEST and LIVE Pre migration testing
- Review of project plans and estimates for 16/17 and 17/18 will be carried out in April.
Milestones
05-May-2017 | Oracle 12.2 GO/NO GO |
12-May-2017 | Upgrade Oracle 12 GEN DEV/TEST/LIVE instances to Oracle 12.2 |
15-May-2017 | Migrate GEN to Oracle 12.2 |
19-May-2017 | NewsLive Deployment sign off |
22-May-2017 | GENDEV Post-migration Checks |
16-Jun-2017 | GenTEST integration sign off |
16-Jun-2017 | Live environment build for GenLive complete |
30-Jun-2017 | GenTEST Acceptance sign off |
- Approved budget
- 306.0 days
- Activity this month
- 20.0 days
- Activity this year
- 139.0 days
- Activity to date
- 145.0 days
- Estimate to complete current year
- 71.0 days
- Estimate to complete future years
- 90.0 days