Organisation
Work/Task Breakdown
Plan | Project Brief, Risk, Estimation and Plan | Project Team |
Analysis | Complete a review of Top and Medium Priority Services to understand level of resilience (full, partial, none) | Development Technology |
Execute | Consider, review and agree Decision Tree scenarios for failover Develop, Test and Implement a mechanism command to make decision to failover Utilise Dataguard to configure Application to initiate Database failover for an ORACLE application | Development Technology Development Team (tbc)
|
Execute | Events Booking (other candidates being explored are Wiki and Learn as Events Booking database is held in Apps Dev database tier) Development
| Development Technology Techology Management Application Management Project Services Service Management |
Execute | Events Booking (other candidates being explored are Wiki and Learn as Events Booking database is held in Apps Dev database tier) Test
| Development Technology Techology Management Application Management Project Services Service Management |
Execute | EBIS Online / WebCentral Development
| Development Technology Techology Management Application Management Project Services
|
Execute | EBIS Online / WebCentral Test
| Development Technology Techology Management Application Management Project Services Estates |
Deploy | EBIS Online / WebCentral Production
| Development Technology Techology Management Application Management Project Services Estates |
Deploy |
| Project Team |
Close |
| Project Team |
Resources Skills and Cost
- IS Applications Development Technology - Database Administrator - 33 days
- IS Applications Technology Management - Database Administrator - 16 days
- IS Applications Application Management - Application Support - 16 days
- IS Applications Project Services - Project Manager - 30 days
- (IS Applications Development Software - Developer) - 5 days
The project will re-estimate following the failover review of Top and Medium Priority Services and confirm candidate application for initial failover testing.
Project Governance
Stefan Kaempf as Project Sponsor and Maurice Franceschi as Programme Manager - Monthly INF programme reviews, monthly status reporting and project team meetings to be held every two weeks.
Communication with Business Area Owner / Service Manager of application candidates