Work/Task Breakdown

StageTask
Planning/System DesignPrep work: Review TAD and Upgrade Documention
  
Build/Testing and Acceptance BambooUpgrade Bamboo and document upgrade in build doc
 Plugin Investigation
 Testing and Acceptance
  
Deployment - BambooUpgrade Bamboo (including plugin fix)
 Testing and Acceptance
 Handover to Technology Management
  
CITESTER Upgrade from CF9 to CF11Setup CF 11 environment for dev,beta,test,live
 Migrate dev, beta,test and live CITESTER applications to CF11
 Test applications and Bamboo deployment to CF11
 Update documentation on process of testing Bamboo following Upgrade

 

Resources Skills and Cost

The project has been estimated at 20 days IS Apps effort. 

Project Info

Project
Bamboo Upgrade 2016
Code
INF117
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
Gillian Henderson
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
18-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
26-May-2016
Programme Priority
10
Overall Priority
Normal
Category
Compliance