Report for October 2015
- Report Date
- October 2015
Report for October by Morna Findlay
Achievements this period
- project initiated
- project manager appointed
- project brief drafted by project manager and circulated to sponsor and stakeholders
- Kick off and intial meetings held
Next Steps
- Achieve end of planning
- prepare communications plan with stakeholders
- Agree signoff of end of grace period with stakeholders and project sponsor
- deliver enforcement of second challenge
The prohect RAg status is GREEN
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days