June 2016

Report Date
June 2016

Achievements in Last Period

  • Additional work has been done with SCOM on the linux stack for Learn.
  • Feedback on SquaredUp sample dashboards consolidated for review by project team and wider group.
  • The wider project group met on 28/06/16 to review the additional work agreed at the 15/04/16 meeting.
  • It was agreed that SCOM (with 3rd party tools to improve the out of the box functionality) provided useful information however there was consensus that it could not function as the "single pane of glass" which had been hoped for (see issues below).

 

 

Issues

The wider group met 28/06/16 to review the work agreed 25/04/16 and after much discussion reached consensus that:

  • SCOM could not be used without 3rd party tools to deal with limitations
  • SCOM (even with 3rd party tools) does not provide sufficient functionality to meet the needs across IS
  • Recommendation will be to not proceed further with SCOM; report will provide rationale from the wider group of Apps and ITI staff and will be completed in July. It is possible the actual closure may be pushed into August but this would only be expected to require 0.5d or less.

 

Next Steps

  • Complete recommendations report.
  • Close Project

 

The project current status is AMBER due to staff availability to complete the recommendations report.

 

Milestones

30-Jun-2016Pilot Dashboards
30-Jun-2016Recommendations
15-Jul-2016Close
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
70.0 days
Activity this month
2.0 days
Activity this year
34.0 days
Activity to date
34.0 days
Estimate to complete current year
6.0 days
Estimate to complete future years
0.0 days

Project Info

Project
System Monitoring Pilot
Code
INF113
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
21-Oct-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
16-Sep-2016
Programme Priority
7
Overall Priority
Normal
Category
Discretionary