March 2016

Report Date
March 2016

Achievements in Last Period

  • Basic dashboards for Learn built against Test (milestone not complete).
  • Microsoft "Chalk & Talk" sessions completed with ITI w/c 14/03/16.

 

Issues

  • MS System Center UI only compatible with Internet Explorer; an inconvenience but outweighed by benefits; however this could be an issue for some IS stakeholders; likewise presentation on non-Windows PCs; there do appear to be Third Party solutions which avoid the need for IE (and would assist with developing more sophisticated dashboard capability than is available out of the box), with associated licensing costs.
  • PM has agreed with Project Sponsor that a face to face meeting with all key stakeholders is necessary to cover the above and agree whether to continue with SCOM / the project.
  • PM has agreed with Project Sponsor to liaise with ITI to arrange a conference call with Microsoft to explore options for the above, ahead of the face to face meeting.

 

Next Steps

  • Project team and key stakeholders to meet and cover above issues; decide whether to continue or halt project.
  • (If agreement is to continue) review budget, estimates, and replan milestones. 

 

Milestones

(NB these are to be reviewed pending Project Status review meeting)

03-Mar-2016Pilot Service 2 - Linux
07-Apr-2016Pilot Service 3 - Corporate
05-May-2016Recommendations
05-May-2016Delivery
19-May-2016Close
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
Change Status
Activity
Approved budget
120.0 days
Activity this month
4.0 days
Activity this year
23.0 days
Activity to date
23.0 days
Estimate to complete current year
92.0 days
Estimate to complete future years
0.0 days

Project Info

Project
System Monitoring Pilot
Code
INF113
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
21-Oct-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
16-Sep-2016
Programme Priority
7
Overall Priority
Normal
Category
Discretionary