February 2016

Report Date
February 2016

Achievements in Last Period

  • Basic dashboards for UniDesk built (milestone complete).
  • Learn architecture documented for SCOM configuration which is now in progress.

 

Issues

  • No major issues.

 

Next Steps

  • Complete setup for Learn on SCOM.
  • Review milestones and estimates.
  • Microsoft "Chalk & Talk" sessions planned with ITI w/c 14/03/16 to build on SCOM knowledge.
  • Go / No go decision on configuration of SCOM for efin.

 

Milestones

03-Mar-2016Pilot Service 2 - Linux
07-Apr-2016Pilot Service 3 - Corporate
05-May-2016Recommendations
05-May-2016Delivery
19-May-2016Close
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
120.0 days
Activity this month
6.0 days
Activity this year
18.0 days
Activity to date
18.0 days
Estimate to complete current year
100.0 days
Estimate to complete future years
0.0 days

Project Info

Project
System Monitoring Pilot
Code
INF113
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
21-Oct-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
16-Sep-2016
Programme Priority
7
Overall Priority
Normal
Category
Discretionary