January 2016
- Report Date
- January 2016
Achievements in Last Period
- End of planning approved.
- Pilot SCOM infrastructure built.
- UniDesk architecture documented for SCOM configuration which is now in progress.
Issues
- No major issues.
Next Steps
- Complete initial setup for UniDesk on SCOM.
- Review milestones and estimates.
- Begin documentation on Learn architecture.
Milestones
04-Feb-2016 | Pilot Service 1 - Windows |
03-Mar-2016 | Pilot Service 2 - Linux |
07-Apr-2016 | Pilot Service 3 - Corporate |
05-May-2016 | Recommendations |
05-May-2016 | Delivery |
19-May-2016 | Close |
- Approved budget
- 120.0 days
- Activity this month
- 5.0 days
- Activity this year
- 12.0 days
- Activity to date
- 12.0 days
- Estimate to complete current year
- 109.0 days
- Estimate to complete future years
- 0.0 days